The completion date for the massive dock replacement project at the Port of Anchorage has been pushed back to 2021 from a target of 2011 set before major construction began.

The price tag, which was $360 million as of 2005, has escalated to $1 billion.

Some engineers are questioning whether the new dock can even be built as designed. Much of the work done in 2010 involved dismantling construction from just a year earlier. Numerous sheets of steel that were planted in Cook Inlet as part of the dock expansion have been ripped up and now lie stacked in twisted and warped piles at the port.

Read the rest in the Anchorage Daily News